New Building Construction Progress

Follow along week by week as our new Junior Learning Centre and Administration Offices are constructed.

October
Week 1 - 3: 6th October - 24th October

Weather has been breezy the past month, with clear skies to help the build along. We can finally visualise its structure and layout - great progress! Recent developments include:

▪️Completed wall framing, as have most of the steel works

▪️Delivered windows set to be installed in the coming weeks

▪️Established main services under the main driveway with electricity to be added to the main switchboard next week

▪️Completed civil works around the outside of the building ready for concrete paths to be poured.

October build 2025 1

August
Week 12 - 16: 23rd July - 26th August

The weather has not been kind to us in the last month, making building progress quite difficult. However, the works that have been occurring include:

▪️Upper-level cement slab has been poured

▪️Drainage works

▪️Landscape preparations

▪️We farewelled rooms PA7 and PA8.

August build

July 2025
Week 11: 16th - 22nd July

▪️ Lower-level cement slab has been poured

▪️Temporary retaining wall built

▪️Services pipes (water, electricity) roughed in on the upper-level.

Week 11 build

June 2025
Week 7: 18th - 24th June

▪️Screw pile placement discovered a septic tank, which had to be removed

▪️Screw pile placement concluded

▪️Soil replacement to cover screw piles took place

Week 7 build

Week 6: 11th - 17th June

▪️Stormwater trenches continued to be dug

▪️The 'envelope' of the building continued

▪️Screw pile placement commenced 

Week 6 build

Week 5: 4th - 10th June

▪️Stormwater trenches continued to be dug

▪️The 'envelope' of the building continued

▪️The building site area continued to be prepped for screw piles which will be placed in the coming weeks

Week 5 build

May 2025
Week 4: 28th May - 3rd June

▪️60 truckloads of dirt arrived

▪️Trenches for stormwater and sewage were dug

▪️ The 'envelope' of the building was laid out

Week 4 build

Week 2 and 3: 14th - 27th May

▪️The site sheds arrived

▪️Site preparation continued

▪️Staff car park asphalt removed

Week 2 and 3 build

Week 1: 7th - 13th May

▪️The site was secured

▪️Trucks, equipment and site sheds arrived on site

▪️Concrete from around the PA building and the car park was removed

▪️Bollards from the oval removed 

▪️Trees removed (for every tree removed, at least 3 will be planted on site in its place)

Week 1 build 