New Building Construction Progress
Follow along week by week as our new Junior School Learning Centre and Administration Offices are constructed.
Week 6: 11th - 17th June
▪️Stormwater trenches continued to be dug
▪️The 'envelope' of the building continued
▪️Screw pile placement commenced
Week 5: 4th - 10th June
▪️Stormwater trenches continued to be dug
▪️The 'envelope' of the building continued
▪️The building site area continued to be prepped for screw piles which will be placed in the coming weeks
Week 4: 28th May - 3rd June
▪️60 truckloads of dirt arrived
▪️Trenches for stormwater and sewage were dug
▪️ The 'envelope' of the building was laid out
Week 2 and 3: 14th - 27th May
▪️The site sheds arrived
▪️Site preparation continued
▪️Staff car park asphalt removed
Week 1: 7th - 13th May
▪️The site was secured
▪️Trucks, equipment and site sheds arrived on site
▪️Concrete from around the PA building and the car park was removed
▪️Bollards from the oval removed
▪️Trees removed (for every tree removed, at least 3 will be planted on site in its place)